Southside Library, Construction Progress, November/December, 2005 :




December 27   

Building Progress
Southside Library is really coming along. Still flat, nothing rising up into the air yet, but the whole thing looks, well, real.

The architects notes for this week say, "Work in progress: a. Structural concrete at the interior of the building is complete, and the radiant piping is in place at the south side of the building. b. Electricians are installing the conduit for below-slab locations. c. Locations have been laid out for columns outside the heated area of the building."





December 27   





December 19   

Radiant Tubing & Rebar Grid
This week's notes from the architect: "a. Concrete is being placed for column bases on the interior of the slab and some on the perimeter. b. Rebar grid has been set and some of the radiant tubing has been placed in the south part of the slab. Tomorrow, the base course will be placed on the north side of the slab, and the rebar grid will be set over that. c. The concrete subcontractor will close the footprint of the building. There is a portion of the stem wall that has been left open for vehicular access."
radiant tubing


December 19   

Radiant Tubing & Rebar Grid
Notice Capital High on the skyline...
rebargrid, high school in background



December 13   

Progressing in Winter Weather
This week Administration met with the architects to make final decisions on colors for both exterior & interior. (Even though the future interior, or any color but mud brown and concrete grey, is a bit hard to imagine at this point.)
workmen working


December 13   

Also this week the gas lines are coming in, and they are working on the retaining wall in the parking lot.
bulldozer with headlight



December 5   

Still Readying for the Slab...
The crushed rock in this photo is to go under the slab. One hundred fifty conduits will be laid in the crushed rock before the pour, 100 of them for the data room.
crushed rock


December 5   

pipes and conduit



November 22   

It's beginning to look like a building...
Both the electricians & plumbers were onsite Monday installing under-slab and within-slab pipes & conduit.
foundation work


November 22   

pipes and conduit


November 22   

conduit



November 14   

After a Pour
There are no pictures of this week's big milestone: 150 data lines are being laid so they will be under the concrete slab... ready to pour



November 7   

River of Concrete concrete in the trench



November 1   

Almost ready for the first pour!! ready to pour


November 1   

ready to pour


November 1   

Almost ready for the first pour!! ready to pour